Case Study: New system in and running in four hours

Louis Dreyfus Commodities operates an ethanol plant in Norfolk, Nebraska. The plant needed a new operating system, but could not afford to lose any production time. Trident worked with plant managers to design a system and process that could be installed during a scheduled 3-day outage. For 12 weeks, teams did pre-engineering work in Wisconsin with installation designed to take hours instead of days. On site, engineers removed an APACS DCS, then installed a customized cabling system to use existing […] Read More