Deadline drives creative solutions in DCS installation for Elkhorn Valley Ethanol

Posted on by Trident

There’s nothing like a critical deadline to spark creative engineering solutions. Trident was given only 3 days to install and startup a new DCS for Elkhorn Valley Ethanol plant. The project had more than 1,500 I/O connections that would require hours of painstaking installation and testing. Trident’s teams estimated it could take about a week […]

Posted in General | Comments Off on Deadline drives creative solutions in DCS installation for Elkhorn Valley Ethanol